Summary
- Islamabad: Questions over financial demands amounting to hundreds of millions of rupees, prolonged delays in building approvals and an unresolved ground rent dispute have surfaced before a Senate panel, which was informed that the National University of Sciences and Technology (NUST) was facing approximately Rs 540 million in building related charges and a further penalty of Rs 472 million despite claiming to have deposited Rs 35 million in annual ground rent in advance up to 2035.
- NUST representatives told the committee that accumulated building related charges had reached approximately Rs 540 million, creating a heavy financial burden on the educational institution.
- NUST representatives informed the committee that the university had already spent approximately Rs 40 million on preliminary wastewater treatment measures.
Islamabad: Questions over financial demands amounting to hundreds of millions of rupees, prolonged delays in building approvals and an unresolved ground rent dispute have surfaced before a Senate panel, which was informed that the National University of Sciences and Technology (NUST) was facing approximately Rs 540 million in building related charges and a further penalty of Rs 472 million despite claiming to have deposited Rs 35 million in annual ground rent in advance up to 2035.
The Capital Development Authority (CDA) also disclosed that the ground rent issue was linked to an audit objection concerning approximately Rs 735 million in unrecovered dues, which had been referred to the Public Accounts Committee.
The disclosures raised serious questions about the calculation of government dues, delays in official approvals and the financial burden being placed on one of Pakistan’s leading public universities.
The matter came under discussion during a meeting of the Subcommittee of the Senate Standing Committee on Science and Technology, held at Parliament House on November 25, 2026, under the chairmanship of Senator Dr Afnan Ullah Khan.
NUST representatives informed the committee that the university had been facing difficulties in obtaining building plan approvals from CDA for several years.
According to university officials, the original layout plan was submitted for approval in 2003, but the approval process remained pending for several years while the university continued developing its educational and residential infrastructure.
They said delays and the absence of an approved master plan during the earlier period affected subsequent building approvals and resulted in substantial penalties and additional charges.
NUST representatives told the committee that accumulated building related charges had reached approximately Rs 540 million, creating a heavy financial burden on the educational institution.
The university maintained that it had submitted building drawings and relevant documents to CDA on several occasions, but the approval issues remained unresolved.
Responding to the concerns, CDA officials stated that the authority had no existing mechanism to waive or reduce the applicable building plan approval charges.
They also raised concerns about construction undertaken by NUST beyond the originally approved layout plan.
Senator Dr Afnan Ullah Khan questioned why the approval process had remained unresolved for so many years and expressed concern over the financial demands being imposed on the university.
He observed that a major educational institution should not be treated in the same manner as a commercial development project when determining applicable charges.
The chairman maintained that imposing a financial burden of approximately Rs 540 million could adversely affect the university’s educational resources.
He directed NUST to submit complete building plans, drawings, payment receipts and supporting documentary evidence to CDA for verification.
The committee specifically sought records concerning construction carried out after the approval of the university’s master plan in 2012.
The chairman directed CDA to examine the documents, process pending building approvals and place the matter before its Board for consideration of a one time waiver of applicable charges.
He also announced that a formal letter would be issued to the CDA Board in support of the university’s request.
The committee directed both institutions to resolve their outstanding differences before the next meeting rather than allowing the matter to remain pending through repeated correspondence.
Another major financial controversy concerned annual ground rent and penalties.
NUST informed the committee that development charges had already been settled according to the development work carried out.
Regarding annual ground rent, university representatives stated that approximately Rs 35 million had been calculated and deposited with CDA in advance up to the year 2035.
However, they informed the committee that a further penalty of Rs 472 million was subsequently imposed.
CDA officials explained that the dispute was connected to an audit objection involving non recovery of annual ground rent amounting to approximately Rs 735 million.
They said the matter had been referred to the Public Accounts Committee for consideration.
The chairman expressed concern over the dispute and emphasized that the payment already made by NUST and its status as an educational institution should be considered before reaching a final decision.
He assured the committee that he would take up the matter with the concerned officials at the Accountant General Pakistan Revenues level.
CDA was directed to revisit the case, explain the university’s position to the competent authorities and pursue its resolution through the appropriate procedure within one to two months.
CDA officials assured the committee that the matter would be resubmitted to the competent authority.
Another serious issue concerned NUST’s prolonged water supply problems.
Officials informed the committee that a water supply scheme originally planned in 2005 to provide water from Allah Ditta had faced delays because of land related issues.
The project remained incomplete more than two decades after it was initially planned.
The Federal Government Employees Housing Authority (FGEHA) had requested Rs 5.5 million from NUST for the scheme, of which Rs 3.5 million had been received, leaving Rs 2 million outstanding.
Officials assured the committee that the pipeline work would be completed within four months.
However, NUST representatives expressed serious concern that the university was receiving no water through the proposed scheme or any alternative source.
They informed the committee that the earlier water supply had stopped after June because tube wells had become nonfunctional.
The university also expressed concern that water supply could remain uncertain even after the pipeline was completed.
Senator Dr Afnan Ullah Khan questioned why water supply had been discontinued despite previous commitments and directed the authorities to ensure uninterrupted provision.
He also sought a report on the number of nonfunctional tube wells. The chairman directed that water from Khanpur Dam should become available after completion of the pipeline within four months.
NUST representatives said the water shortage was also affecting plans to expand hostel accommodation, which was needed because of growing student requirements.
The committee also examined serious sewerage and environmental problems affecting the university.
Officials informed the panel that untreated wastewater passing through Sector G 13 was entering a natural water stream, while the relevant drainage system fell under the responsibility of FGEHA.
FGEHA officials stated that delays in acquiring land in Sectors G 12 and G 14 had affected the sewerage project.
NUST representatives informed the committee that the university had already spent approximately Rs 40 million on preliminary wastewater treatment measures.
However, these arrangements were insufficient to resolve the problem completely. The university complained that untreated wastewater was producing an unpleasant smell in surrounding areas and that a proper treatment plant was urgently needed.
Officials estimated the required wastewater treatment plant would cost approximately Rs 105 million. NUST expressed willingness to provide land for the facility but maintained that it lacked the financial resources necessary for construction.
The chairman directed FGEHA either to establish the wastewater treatment plant itself or provide the necessary funds to NUST.
He stressed that the environmental problem must be addressed without further delay. The committee also discussed a proposal for expanding NUST’s educational facilities to Karachi.
Senator Dr Afnan Ullah Khan observed that Karachi, with a population exceeding 22 million, required greater access to quality higher education.
NUST representatives informed the committee that approximately 100 acres of land would be needed to establish a larger campus in Karachi.
However, obtaining such a large piece of land within the city would be difficult.
The chairman encouraged NUST to develop a comprehensive proposal and said suitable land could also be considered outside the main city.
He suggested introducing new academic programmes, including a business school and facilities for technology, innovation and entrepreneurship.
NUST agreed to place the proposal before its Board and present its response at the next meeting.
During the proceedings, the chairman also sought assurances that land allocated to NUST was being used exclusively for educational purposes and in accordance with the approved master plan.
University representatives assured the committee that the land was being utilized solely for university related activities and that a boundary wall had been constructed around the premises.
Senator Husna Bano attended the meeting along with senior officials from NUST, CDA, FGEHA and other concerned departments.