Margalla Avenue N5-M1 extension project 43% complete, Sangjani Interchange nears completion

Asad Kharal
4 Min Read

Summary

  •   ISLAMABAD:  Construction work on the Margalla Avenue N5 to M1 Extension and Sangjani Interchange project is progressing rapidly, with 43 per cent of the overall development work completed, according to the Capital Development Authority (CDA).
  • Construction Work Progresses on Multiple Sections According to the CDA, development work on the approximately 2.7-kilometre-long extension of Margalla Avenue is advancing across all sections falling within the Islamabad Capital Territory (ICT).
  • Underpass Structural Work Completed The CDA has confirmed that the structural construction of the underpass included in the Margalla Avenue Extension project has been completed.
AI Generated Summary

 

ISLAMABAD:  Construction work on the Margalla Avenue N5 to M1 Extension and Sangjani Interchange project is progressing rapidly, with 43 per cent of the overall development work completed, according to the Capital Development Authority (CDA).

The authority said construction activities were continuing around the clock to ensure timely completion of the project. Work is being carried out on multiple sections simultaneously under the directions of CDA Chairman and Chief Commissioner Islamabad.

The project is expected to improve road connectivity, provide easier access to Islamabad and facilitate commuters travelling between different cities, particularly those coming from Khyber Pakhtunkhwa (KP).

Construction Work Progresses on Multiple Sections

According to the CDA, development work on the approximately 2.7-kilometre-long extension of Margalla Avenue is advancing across all sections falling within the Islamabad Capital Territory (ICT).

Construction of the loops and ramps included in the project has also entered its final stages. Meanwhile, work on the service road connecting with the main carriageway is progressing steadily.

The authority is undertaking construction activities simultaneously to accelerate development and ensure that different components of the project are completed within the timeframe.

Underpass Structural Work Completed

The CDA has confirmed that the structural construction of the underpass included in the Margalla Avenue Extension project has been completed.

Concrete walls and footing slabs of the underpass have been constructed, while earthwork filling on its right and left sides is expected to be completed shortly.

The completion of these structural components marks an important step towards the overall progress of the road infrastructure project.

Sangjani Interchange Nears Completion

Work on the Sangjani Interchange, one of the major components of the development scheme, is also moving forward.

According to the CDA, piling work at the interchange has been completed, while steel fixing activities are currently underway. The girder-related work has also been completed, and the remaining excavation work is expected to be finished soon.

The interchange is expected to play a significant role in connecting Margalla Avenue with the N5 and M1 Motorway, improving traffic movement for commuters entering and leaving the federal capital.

N5 Bridge and Culvert Construction

Progress has also been reported on the N5 Bridge, where piling work and excavation of abutments on both sides have been completed.

Similarly, construction of four out of the five culverts included in the project has been finished, while work on the remaining culvert is continuing.

These structures are essential components of the road network and will support smoother traffic movement once the entire project becomes operational.

CDA Chairman Directs Timely Completion

CDA Chairman Sohail Ashraf has directed the concerned departments and construction teams to maintain high-quality standards and complete the project within the stipulated timeframe.

He described the development scheme as an important gateway for citizens travelling to Islamabad from other cities, particularly Khyber Pakhtunkhwa.

The chairman said the completion of the project would make travelling within and outside the federal capital more convenient, especially for people accessing Islamabad International Airport.

Improved Connectivity and Reduced Traffic Congestion

Once completed, the Margalla Avenue Extension will provide a direct connection between N5 (G.T. Road) and the M1 Motorway through Sangjani.

The project is expected to offer commuters a faster route towards Islamabad International Airport while reducing traffic pressure on major roads, including Srinagar Highway and Kashmir Highway.

It will also establish an alternative entry point for vehicles arriving from KP, Punjab and the northern areas, improving overall accessibility and connectivity to the federal capital.

We welcome your contributions! Submit your blogs, opinion pieces, press releases, news story pitches, and news features to opinion@minutemirror.com.pk and minutemirrormail@gmail.com
Share This Article
Leave a Comment

Leave a Reply

Your email address will not be published. Required fields are marked *